Ports & Docks Major Projects

2017/2018 Ports Capital Projects

• Replacement of select cross braces, rub rails and other components at Eastbourne (Keats Island) - Completed
• Replacement of select piles and rub rails at Port Graves (Gambier Island) - Completed
• Replacement or removal of select piles and hardware at Halfmoon Bay - Completed
• Replacement of select cross braces at Hopkins Landing - Completed
• Replacement of Gambier Harbour Float A - Late February or March, 2018
• Additional capital projects supported by Canada 150 Grant - February and March 2018

The SCRD will provide advance notice of work to communities and will work with contractors to minimize disruptions. Please visit this page for updates.

Notice to West Bay Gambier Island Dock Users

The Sunshine Coast Regional District with support from Western Economic Diversification Canada will be replacing the decking on the approach to the West Bay Dock between February 20 and April 19, 2018. During this time please arrange to use other dock facilities such as Gambier Harbour or New Brighton. If you have any questions please contact the SCRD at 604-885-6800.

Notice to Halkett Bay Gambier Island Dock Users

The Sunshine Coast Regional District with support from Western Economic Diversification Canada will be conducting repairs to the Halkett Bay float from February to March 2018. Expect service interruptions during this time period. Exact dates of float closure will be communicated when they become available. If you have any questions please contact the SCRD at 604-885-6800.

Gambier Harbour Float Replacement Project

The Sunshine Coast Regional District with support from Western Economic Diversification Canada will be replacing the large float at the Gambier Harbour Dock in late February or March 2018. Installation dates when the float will be out of service will be provided as soon as confirmed. Expect service interruptions during this time period. If you have any questions please contact the SCRD at 604-885-6800.

Seasonal maintenance will also be taking place at other SCRD ports. Dates may change due to weather. During these times there may be service impacts including reduced access to floats. Thank you for your patience and for watching for construction vessels while we work to maintain docks. For further information please contact the SCRD at 604-885-6800 or info@scrd.ca.

 

Keats Landing Eastbourne Hopkins Landing Gambier Harbour West Bay Port Graves Halkett Bay